Change order form for contractors: what to put on it (free template)

Most money lost on a job isn’t lost in the bid. It goes out the door as “while you’re here, can you…” work that never got priced or signed. A one-page change order, signed before the extra work starts, fixes that. Here is every line it needs, with an example for each.

The 16 lines of a change order

LineWhat goes there
Project / job name and addressSmith kitchen remodel, 12 Oak St.
Original contract date and numberContract #2026-031, signed Sept 8, 2026
Change order numberCO-03 (number them in order, never reuse one)
Requested byOwner, contractor, or architect, and the date asked
Description of the changeWhat is added, removed or substituted, in plain words, with locations and quantities
ReasonOwner request, hidden condition found, design change, code requirement
LaborHours × rate, by trade
Materials and equipmentItemized, with quantities
Subcontractor costsTheir written price, attached
Overhead and profit on the changeYour stated markup, applied the same way as in the contract
Credit for work removedIf the change deletes work, show the credit as a minus line
Change order totalAdd or deduct, in dollars
Revised contract sumOriginal sum, plus or minus all approved change orders to date
Schedule impactNumber of working days added (or “none”) and the new completion date
Payment terms for this changeBilled with the next progress payment, or due on approval
Signatures and datesOwner and contractor; work starts after both sign

Four rules that keep change orders from turning into arguments

  1. Sign before you build. Put it in the original contract that extra work starts only after a signed change order. A text message saying “go ahead” is better than nothing, but follow it with the form the same day.
  2. Price it the same way you priced the bid. Use the same labor rates and the same overhead and profit markup the contract states, so the customer can’t say you inflated it.
  3. Always show the schedule impact. Extra work usually means extra days. Writing “none” is fine when it’s true; leaving it blank invites a delay dispute later.
  4. Keep a running total. Every change order shows the revised contract sum, so nobody is surprised at the final invoice.

This is a general template, not legal advice. Change order, home-improvement contract and lien rules vary by state; check your state’s licensing board and have an attorney review your contract and forms.

Want it as a ready-to-fill form?

The Contractor Bid Kit includes a fillable change order (PDF and Word) with these lines, plus an estimate and takeoff worksheet, proposal template, scope and exclusions checklist, progress payment schedule, bid follow-up scripts and an Excel bid calculator. $49 one-time. This page stays free either way.

Get the Contractor Bid Kit — $49 Free bid markup calculator

Templates and worksheets, not legal, tax or accounting advice. Contract, licensing, deposit, retainage, lien and notice rules vary by state: check your state licensing board and local lien rules, and have an attorney in your state review your contracts before you use them. No guaranteed results.